Approving the Second Amendment to the Interlocal Cooperation Agreement between the City of Pflugerville and Travis County for the East Pflugerville Parkway/Jesse Bohls Roadway Improvements Project, addressing detention pond responsibilities and additional construction phase funding, and authorizing the City Manager to execute the same.
Summary
This agenda item requests approval of the Second Amendment to the Interlocal Cooperation Agreement (ILA) between the City of Pflugerville and Travis County for the East Pflugerville Parkway/Jesse Bohls Roadway Improvements Project. The amendment clarifies the parties’ responsibilities related to stormwater detention and establishes funding obligations for the remaining construction phase of the project. This item supports the Infrastructure pillar of the City’s Strategic Plan.
The original ILA was executed in October 2019 and amended in March 2022 to address funding responsibilities for the project. Since that time, final engineering design, plans, and specifications have been completed, allowing the project to advance into full construction. This Second Amendment is necessary to clarify operational responsibilities and funding for the remaining construction activities.
The amendment formalizes the use of an existing City-owned detention pond located at the City’s water treatment plant to accommodate stormwater runoff from the roadway project in compliance with Atlas 14 requirements. Under the amendment, the City will be responsible for ensuring the detention pond has adequate capacity to accommodate the project’s runoff and will retain full responsibility for its design, operation, maintenance, and any future modifications, at no cost to Travis County. Travis County will retain the right to inspect the facility with advance notice.
Additionally, the Second Amendment establishes the remaining construction phase funding responsibilities between the City and Travis County. The East Pflugerville Parkway corridor is approximately 57.25% within the City of Pflugerville and 42.75% within Travis County’s jurisdiction, and the parties have agreed to allocate construction costs accordingly. Estimated construction costs, including a 12% contingency and a 5% construction management fee, are documented in Attachment A to the amendment.
The amendment identifies Travis County’s share of the remaining construction phase costs for the County portion of the project as not to exceed $7,233,694.12. Travis County will deposit these funds into an escrow account with the City within 30 days of full execution of the amendment. Any additional funding beyond this amount would require approval by the Travis County Commissioners Court.
Except as specifically amended, all other terms and conditions of the original ILA and its prior amendment remain in full force and effect.
This item is supported by the Mobility Infrastructure and Connectivity pillar of the City’s Strategic Plan.
Prior City Council Action
August 29, 2019: Approved a professional engineering services agreement with LJA Engineering, Inc. in the amount of $824,160 for design of the East Pflugerville Parkway/Jesse Bohls Extension and Realignment Roadway Project.
August 29, 2019: Approved a Resolution for an interlocal agreement with Travis County for project management, project development, and fiscal obligations related to the East Pflugerville Parkway/Jesse Bohls Project.
January 12 ,2021 Approved a professional engineering services agreement with LJA Engineering, Inc. in the amount of $355,494.75 for design of the East Pflugerville Parkway/Jesse Bohls Extension and Realignment Roadway Project.
January 28, 2022: Approved a Resolution for the amendment of the interlocal agreement with Travis County for project management, project development, and fiscal obligations.
February 8, 2022: Approved a professional services supplemental agreement with LJA Engineering, Inc. in the amount of $401,348.75 for additional engineering services.
October 28, 2025: Approved a construction contract with Patin Construction, LLC in the amount of $10,745,101.35 for the East Pflugerville Parkway/Jesse Bohls Extension and Realignment Roadway Project.
Deadline for City Council Action
Action is requested on January 13th, 2026
Funding Expected: Revenue __ Expenditure _X_ N/A _X_
Budgeted Item: Yes _X_ No __ N/A __
Budget Source: __CO bonds, 2023A and 2025 issuances, TIA and RIF_______
Amount: ___Travis County contribution not to exceed $7,233,694.12 (escrowed with the City)_____
1295 Form Required? Yes _X_ No __
Legal Review Required: N/A __ Required _X_ Date Completed: ____December 4th, 2025_______
Supporting documents attached:
Second Amendment to the Interlocal Cooperation Agreement between the City of Pflugerville and Travis County
Exhibit A - East Pflugerville Parkway Construction Cost Estimate
Recommended Action
Approve the Second Amendment to the Interlocal Cooperation Agreement between the City of Pflugerville and Travis County for the East Pflugerville Parkway/Jesse Bohls Roadway Improvements Project and authorize the City Manager to execute the same.