Title: Approving a construction contract with G2 CSi in the amount of $940,000 for construction services associated with the Pflugerville Police Department Parking Lot Expansion Project, and authorizing the City Manager to execute the same.
Attachments: 1. Pflugerville Police Dept Parking Lot Expansion Contract

Title

Approving a construction contract with G2 CSi in the amount of $940,000 for construction services associated with the Pflugerville Police Department Parking Lot Expansion Project, and authorizing the City Manager to execute the same.

 

Summary

The proposal being considered with this item was provided by G2 CSi for a construction contract with the City in the amount of $940,000 to perform construction services for the proposed improvements.

 

G2 CSi has successfully completed similar projects with the City on a variety of other smaller construction projects and they are currently a HUB vendor with the State of Texas as a woman-owned business.

 

The  G2 CSi holds a TIPS-USA contract that the City of Pflugerville uses regularly.

 

For governmental agencies such as city or county governments, membership in a purchasing cooperative offers the following benefits:

 

                     Access to competitively procured contracts with quality vendors

                     Savings of time and financial resources necessary to fulfill bid requirements

                     Assistance with purchasing process by qualified TIPS staff

                     Access to pricing based on a “national” high-profile contract

 

Funds have been allocated by City staff to perform proposed improvements to the Pflugerville Justice Center by providing additional storage for existing and future Police Department squad vehicles.

 

The project will consist of developing a portion of adjacent city-owned property west of the Pflugerville Justice Center for expansion of the existing police department parking lot. Parking facility spots were maximized based on available space as a result of proposed detention facilities and the current area occupied by the existing elevated storage tank.

 

The detention facility is designed to capture and mitigate flows from the proposed conditions for the appropriate storm events as indicated in the “City of Pflugerville Engineering Design Guidelines and Construction Standards.” Other aspects of the project also included utility design of proposed conduits for parking lot lighting as well as erosion and sediment controls.

 

Prior City Council Action

NA

 

Deadline for City Council Action

May 14, 2024

 

Funding Expected: Revenue __ Expenditure _X_ N/A __

Budgeted Item: Yes _X__ No __ N/A __

Amount: _$940,000_______

1295 Form Required? Yes _X_ No __

Legal Review Required: N/A __ Required _X__ Date Completed: ___________

 

Supporting documents attached:

Pflugerville Police Dept Parking Lot Expansion Contract

 

 

Recommended Action

Staff recommends approving a construction contract with G2 CSi in the amount of $940,000 for construction services associated with the Pflugerville Police Department Parking Lot Expansion Project and authorizing the City Manager to execute the same.