Title
Approving a construction contract with Garney Companies, Inc. in the amount of $9,185,585.89 for the Sorento Wastewater Interceptor Phase 2 project, and authorizing the City Manager to execute the same.
Summary
Request approval to award a construction contract with Garney Companies, Inc. in the amount of $9,185,585.89 associated with the Sorento Wastewater Interceptor Phase 2 project. This project supports the infrastructure pillar of the City’s Strategic Plan and Comprehensive Plan by providing a safe, resilient infrastructure for our citizens, and is identified in the Utility CIP budget. The project is identified as (WW2003) in the Capital Improvement Plan FY2025-FY2029.
The Sorento Wastewater Interceptor Phase 2 project includes the installation of approximately 8,322 LF of 36-inch fiber reinforced polymer (FRP) wastewater line and 2,618 LF of 18-inch FRP wastewater line, including 25 polymer concrete manholes from Jesse Bohls Dr. to the Verona Lift Station and to Weiss Lane. The project includes open cut and trenchless pipeline installation. The project will convey flows from Verona and Weiss Lane lift stations and existing/future wastewater flows within the Wilbarger wastewater basin to the Wilbarger Creek Regional Wastewater Treatment Facility, which is currently under construction. The project also includes decommissioning the Verona lift station.
Advertisement for the project on the basis of Competitive Sealed Proposals began on April 30, 2025. The City received and opened proposals on May 30, 2025. Eight (8) bids were received for the Project. Each of the submitted proposals were evaluated and scored by a team consisting of City of Pflugerville staff in compliance with the criteria in the Project Manual. Garney Companies, Inc. is the recommended contractor which provides the best value to the City. Consultant has performed a reference check. The advertisement and bid procedures meet the funding requirements of the EPA’s WIFIA and TWDB Clean Water SRF programs.
Contract requires completion within 295/383 calendar days substantial/final respectively.
Prior City Council Action
None
Deadline for City Council Action
6/24/2025
Funding Expected: Revenue __ Expenditure _X_ N/A __
Budgeted Item: Yes _X_ No __ N/A __
Budget Source: TWDB
Amount: $9,185,585.89
1295 Form Required? Yes _X_ No __
Legal Review Required: N/A __ Required _X_ Date Completed: 6/16/2025
Supporting documents attached:
Construction Agreement
Engineer’s Recommendation Letter
Project Location Map
Recommended Action
Approve a construction contract with Garney Companies, Inc. in the amount of $9,185,585.89 associated with the Sorento Wastewater Interceptor Phase 2 project, and authorize the City Manager to execute the same.