Title: Professional services agreement with Quorum Architects, Inc. in the amount of $1,317,230 to provide professional design services associated with the new PAWS building project.
Attachments: 1. Professional Services Agreement, 2. Scope of Services
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Professional services agreement with Quorum Architects, Inc. in the amount of $1,317,230 to provide professional design services associated with the new PAWS building project.

 

Summary

This agenda item requests approval of a Professional Services Agreement (PSA) in the amount of $1,317,230 for Quorum Architects, Inc. to provide design and construction phase services associated with FA2704 - New PAWS Animal Shelter.  The agreement specifically includes:

 

Programming and conceptual design

Schematic Design

Design Development

Construction Documents

Bidding

Construction Contract Administration

On Site Civil Engineering

Survey

Landscape/Irrigation

AV/Technology

Interior Design

Cost Estimation

TDLR Accessibility REview/Inspection

Direct Expenses (travel, printing, etc.)

 

The agreement does NOT include:

 

Off Site Civil Engineering

Geotechnical Engineering

Furnishing, Fixture, and Equipment (FFE) selection and procurement

Extra renderings or videos

Additional cost estimation beyond that listed above

permitting fees

Detailed Audio/visual, access control or security design beyond typical city standards

Storm shelter design

Fast tracking design

Multiple construction packages

Commissioning

Additional studies or permitting other than listed above

 

The schedule is inclusive of having Design Development Drawings complete and Construction Drawings started in time to provide City Council with a detailed (not final) cost estimate sufficient for considering doing a November 2027 bond election.

 

Substantial Completion

N/A

 

Final Completion

N/A

 

Design Completion

October 2027

 

Prior City Council Action

City Council approved $1,300,000 for design with the 2027-31 CIP.

 

Deadline for City Council Action

October 27, 2026

 

Funding Expected: Revenue __  Expenditure X N/A __ 

Budgeted Item: Yes X No __  N/A __

Budget Source: General Fund Reserves                     

Budgeted Amount: $1,300,000

Amount: $1,317,230

1295 Form Required? Yes X No __                     

Legal Review Required: N/A __ Required X Date Completed: 10/15/2026                                          

 

Supporting documents attached:

Professional Services Agreement

Scope of Services

 

Project Schedule

Programming/Conceptual Design - November 2026-January 2027

SDs - February 2027-March 2027

DDs - April 2027-June 2027

CDs - July 2027 - October 2027

 

Recommended Action