Title: Approving a change order in the amount of $138,374 and 7 additional days for the Secondary Colorado River Raw Water Line Project, and authorizing the City Manager to execute the same.
Attachments: 1. Blue Goose Erosion Map, 2. Secondary Colorado River Raw Water Line - Contract 3 - Change Order #5

Title

Approving a change order in the amount of $138,374 and 7 additional days for the Secondary Colorado River Raw Water Line Project, and authorizing the City Manager to execute the same.

 

Summary

Request approval of a Change Order to S.J. Louis Construction of Texas, Ltd. in the amount of $138,374 and seven (7) additional calendar days for work associated with the Secondary Colorado River Raw Water Line - Package 3 (WA-2201).

Following the July 2025 flood event, significant erosion was discovered near Blue Goose Road adjacent to Unnamed Creek, where both the City’s existing 30-inch raw water line and the new 42-inch pipeline are located. In coordination with the Engineer of Record, City staff evaluated options to prevent further erosion and protect both pipelines.

The proposed Change Order includes installing a concrete encasement around the pipelines at this location. This solution will provide long-term protection by limiting future erosion impacts to the encasement, reducing the risk of pipeline exposure or damage.

While similar protective measures were included in other sections of the project during design, this area was not previously identified as vulnerable. Simply restoring soil to original grade would not provide adequate protection against future flood events. This Change Order represents the most efficient and cost-effective approach to safeguard critical infrastructure in this area.

This item is supported by the Residential and Node Development and Economic and Business Development pillars of the Strategic Plan by planning for the City’s infrastructure systems to support the ability to foster these pillars of the Strategic Plan.

 

Prior City Council Action

City Council approved a construction contract with BELT construction of Texas, LLC in the amount of $35,326,497 associated with the Secondary Colorado River Raw Water Line Project on October 22, 2024.

 

City Council approved a construction contract with S.J Louis construction of Texas, Ltd in the amount of $56,665,407.35 associated with the Secondary Colorado River Raw Water Line Project on October 22, 2024.

 

City Council approved a construction contract with Thalle construction company Inc, in the amount of $12,795,000 associated with the Secondary Colorado River Raw Water Line Project on October 22, 2024.

 

Deadline for City Council Action

October 28, 2025

 

Funding Expected: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes _X_ No __  N/A __

Budget Source: _Capital Improvement Project Contingency

Amount: _$138,374_______ 

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A _X_ Required __ Date Completed: ____                     

 

Supporting documents attached:

Secondary Colorado River Raw Water Line - Contract 3 - Change Order #5

Blue Goose Erosion Map

 

Recommended Action

Staff recommends approval of a change order in the amount of $138,374 and 7 additional days for the Secondary Colorado River Raw Water Line Project, and authorizing the City Manager to execute the same.