Title
Approving a professional services supplemental agreement with Kimley-Horn and Associates, Inc. for the Cottonwood West Lift Station and Force Main, in the amount of $93,050, and authorizing the City Manager to execute the same.
Summary
The Cottonwood West Lift Station and Force Main Project is in the 5-year Capital Improvement Plan (Project No. WW 2302). The project was recommended in the 2023 Wastewater Master Plan. This item supports the Infrastructure Pillar of the Strategic Plan.
The original Professional Services Agreement from 2023 was based on the assumption that the project would not be funded through EPA Water Infrastructure Finance and Innovation Act (WIFIA). As a result, the scope of the environmental study outlined in the original agreement does not fully meet EPA requirements. Additionally, the city has decided to combine the force main and gravity interceptor to a single project bid. The gravity interceptor was designed by a different consulting engineering firm contracted by a developer.
Under this amendment, Kimley-Horn will be responsible for conducting an environmental and cultural resources study for the downstream gravity interceptor, as well as performing an additional desktop study for the lift station and force main to ensure compliance with EPA requirements for WIFIA funding. Kimley-Horn will provide bid and construction administrated support for the downstream gravity interceptor project which was excluded from the original agreement.
Prior City Council Action
Pflugerville City Council approved a Professional Services Agreement with Kimley Horn for a total of $1,285,932.08 on March 7th, 2023 council meeting for Preliminary, Design, Bid, and Construction Phase Services.
Pflugerville City Council approved Professional Services Supplemental Agreement #2 for Professional Services for the Project in the amount of $119,462.50 to add pre-procurement, additional drainage and water quality design, as well as additional environmental and cultural resources to the Agreement on the 16th day of November 2023.
Deadline for City Council Action
April 8, 2025
Funding Expected: Revenue ____ Expenditure _X__ N/A____
Budget Source: EPA Water Infrastructure Finance and Innovation Act (WIFIA)
Budgeted Item: Yes __X__ No ___
Amount: $93,050
1295 Form Required? Yes X No ___
Legal Review: N/A______ Required X Date completed: 3/18/2025
Supporting Documents Attached:
Professional Services Supplemental Agreement
Recommended Action:
Approve a Professional Services Supplemental Agreement with Kimley-Horn and Associates, Inc. and authorize City Manager to execute the same.