File #: 2024-1099    Version: 1 Name: Downtown East - Infrastructure PSA
Type: Agenda Item Status: Approved
File created: 11/1/2024 In control: City Council
On agenda: 11/12/2024 Final action: 11/12/2024
Title: Approving a Purchase and Sale Agreement (PSA) with Griffin Swinerton, LLC for infrastructure construction within Downtown East, and authorizing the City Manager to execute the same.
Attachments: 1. Downtown East - Purchase and Sale Agreement (Civil Works), 2. Exhibit A - Draft Installment Payments, 3. Exhibit D - Schedule of Values/GMP, 4. Exhibit E - Civil Works Schedule 11.07.2024, 5. Exhibit F - Developer Conditions & Assumptions 11.07.2024

Title

Approving a Purchase and Sale Agreement (PSA) with Griffin Swinerton, LLC for infrastructure construction within Downtown East, and authorizing the City Manager to execute the same.

 

Summary

Phase One of Downtown East includes the construction of the Multi Generational Recreation Center, City Hall, plaza, retail, and related infrastructure which encompasses utilities, roadwork, parking, and a plaza.  The proposed Purchase and Sale Agreement (PSA) outlines the terms in which Griffin Swinerton, LLC, the master developer of the Downtown East project, will deliver components of the infrastructure to support the project (known as the "Civil Work"). 

 

With each PSA, the City will make installment payments on the guaranteed maximum price for each component of the project.  For this PSA, the guaranteed maximum price to deliver the Civil Work is $24,442,314 for Phase 1A.  Upon final completion and final payment Griffin Swinterton, LLC’s obligations under the PSA for Civil Work will be considered complete.

 

Construction on the Civil Work is scheduled to start in December 2024.

 

The License Agreement (2024-1105), PSA (2024-1099), and MOU (2024-1124) within this agenda, all work in conjunction to deliver the Downtown East project.  

 

This item meets all four of the Council’s Strategic Goals, as well as Goal 2.2 of the Aspire 2040 Comprehensive Plan to pursue a mixed-use project with municipal facilities through a master developer arrangement.

 

Downtown East History

The Downtown East project is located on +/-29 acres located at the northwest corner of Pecan Street and FM 685.  Discussions for Downtown East have included aspirations to leverage the central Pflugerville location to become a mixed-use development with connections to Main Street and the City's hike and bike trail network anchored by the proposed new multi-generational recreation center and new city hall. 

 

An Exclusive Negotiating Agreement (ENA) was approved on March 28th, which established the expectations of the development partnership and performance of preliminary development activities necessary to achieve the goals outlined by City Council for the Downtown East project.  The ENA outlined the general roles, as well as the responsibilities, terms and obligations of both the City and the City's development partners Griffin Swinerton and Catellus. The ENA recognized the need for additional agreements, referred to as Preliminary Development and Definitive Agreements, that come as the development progresses.

 

On November 28, 2023, Council approved a Preliminary Development Agreement (PDA) for the project.  The PDA process for the project is defined as a as a two-phase project with Griffin Swinerton as the master development partner. Within the PDA, Phase One was outlined and consists of all elements required for the delivery of a City Hall and café, Multi-Generational Recreation Center, 10,500sf of retail within the Recreation Center, a plaza, and infrastructure extensions including utilities, surface parking, and Main Street extension from Railroad to FM685. Through the PDA, Griffin Swinerton advanced the designs for Phase One allowing for the project to proceed with a guaranteed maximum price to deliver each facility as well as the infrastructure to support the project.  As part of the PDA, Griffin Swinnerton also committed to funding a minimum of $2.5M towards the delivery of 10,500 square feet of retail within Phase One of the project.  The approval of the PDA also included the master planning and entitlements for Phase Two of the Downtown East project in order to competitively position this portion of the project for future development as market conditions evolve.

 

Funding for improvements within Phase One includes General Obligation (GO) and Certificate of Obligation (CO) bonds, Tax Increment Reinvestment Zone (TIRZ) funds, Pflugerville Community Development Corporation (PCDC) budget allocation, and contributions by Griffin Swinerton. 

 

Future City Council Action

A ground lease for the Downtown East tract will be presented for Council consideration on November 19, 2024. 

 

A professional services agreement related to the Multi Generational Recreation Center and City Hall will be considered by Council in early 2025.  Future consideration related to the retail component of the Multi Generational Recreation Center include commercial condominium documents, parking agreement, and a retail agreement are anticipated for consideration by City Council in early 2025.

 

Prior City Council Action

On August 13, 2024, City Council approved the rezoning of the Downtown East Project to Planned Unit Development (PUD)

On November 28, 2023, City Council approved a Preliminary Development Agreement for the project

On March 28, 2023, City Council approved an Exclusive Negotiating Agreement for the project

On January 10, 2023, City Council approved the selection of Griffin Swinerton and Catellus as the  master development team for the Downtown East project.

On July 26, 2022, City Council authorized staff to proceed with the solicitation of a master developer, project funding, a pursuing a request for funding from the Pflugerville Community Development Corporation (PCDC)

The Downtown Community Stakeholder Committee was appointed by City Council on May 10, 2022 and reappointed on June 14, 2022

Goals were adopted by City Council for the project on April 12, 2022

Professional Services Agreements were approved by City Council January 25 and February 28, 2022 for owner's project representatives and advisor services

 

Deadline for City Council Action

Action is requested on November 12, 2024

 

Funding Expected: Revenue __  Expenditure __  N/A _X_ 

Budgeted Item: Yes __ No __  N/A _X_                     

Amount: ________ 

1295 Form Required? Yes __ No __                     

Legal Review Required: N/A ___ Required _X_ Date Completed: November 7, 2024

 

Supporting Documents

Purchase and Sale Agreement (inclusive of Exhibit B)

Exhibit A - Installment Payment Schedule

Exhibit C - Non-Default Termination Fee Schedule,  to be completed prior to execution

Exhibit D - Schedule of Values/GMP

Exhibit E - Civil Work Project Component Construction Schedule

Exhibit F - Developer Conditions and Assumptions

 

 

Recommended Action

Motion to approve as presented