Pflugerville Banner
File #: 2025-0063    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 1/3/2025 In control: Public Works
On agenda: 2/11/2025 Final action: 2/11/2025
Title: Approving a Discretionary Service Agreement (DSA) with Oncor Electric Delivery in the amount of $498,551 for relocation of overhead to underground facilities associated with Historic Colored Addition Subdivision (HCA) Russell St, Caldwells Ln, Taylor St, and Lincoln Ave Infrastructure Improvements Project, and authorizing the City Manager to execute the same.
Attachments: 1. Discretionary_Service_Agreem, 2. Statement of Charges

Title

Approving a Discretionary Service Agreement (DSA) with Oncor Electric Delivery in the amount of $498,551 for relocation of overhead to underground facilities associated with Historic Colored Addition Subdivision (HCA) Russell St, Caldwells Ln, Taylor St, and Lincoln Ave Infrastructure Improvements Project, and authorizing the City Manager to execute the same.

 

Summary

The City of Pflugerville has been coordinating with Oncor Electric Delivery for the relocation of overhead utilities to underground infrastructure as part of the HCA Project. This effort requires a Discretionary Service Agreement with Oncor to facilitate the removal of existing overhead facilities and the installation of underground components.

 

The agreement outlines Oncor's responsibilities, including procurement and installation of necessary electrical infrastructure. The total cost for these services is $498,551.00, which will cover the relocation of Oncor-owned facilities, excluding any costs associated with third-party joint users attached to Oncor poles. Joint users are currently coordinating with City staff on their relocations to underground.

 

At the January 28th, council approved the construction contract with Joe Bland Construction to work on the underground infrastructure for Phase 1of the project. For Phase 2, Oncor will relocate their facilities above ground to below ground. In Phase 3 Joe Bland will work on the above ground improvements. This project is schedule to start construction in February 2025 and completed by April 2027.

 

This agreement aligns with the City Council’s strategic goal of infrastructure by ensuring reliable electrical service and supporting long-term city development. The relocation process will begin once all necessary approvals and permits are in place.

 

Prior City Council Action

N/A

 

Deadline for City Council Action

February 11,2025

 

Funding Expected: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes _X_ No __  N/A __                     

Amount: _$498,551.00 _______ 

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A __ Required _X_ Date Completed: __January 28,2025_________                                          

 

Supporting documents attached:

Discretionary Service Agreement (DSA)

Statement of Charges

 

Recommended Action

Approve the Discretionary Service Agreement (DSA) with Oncor Electric Delivery.