Pflugerville Banner
File #: 2020-7855    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 9/25/2019 In control: Engineering Dept
On agenda: 4/14/2020 Final action: 4/14/2020
Title: Awarding a construction contract for the 2019 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on El Malino and Bellemeade to M.A. Smith Contracting Company, Inc., the lowest responsible bidder of four (4) bids received on February 27, 2020, in the amount of $406,969.80 and authorizing the City Manager to execute same.
Attachments: 1. BidTab El Malino Bellemeade Feb 20.pdf, 2. CIP CDBG Road Exhibit Map.pdf

Title

Awarding a construction contract for the 2019 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on El Malino and Bellemeade to M.A. Smith Contracting Company, Inc., the lowest responsible bidder of four (4) bids received on February 27, 2020, in the amount of $406,969.80 and authorizing the City Manager to execute same.

 

Summary

The City of Pflugerville previously opened bids for the 2019 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on El Malino and Bellemeade Project on October 3, 2019 after all required notices posted. The bidding process was facilitated through a plan holder website, civcast.com, which is used for all City construction projects. It was determined that rejecting all bids received, and rebidding the 2019 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on El Malino and Bellemeade Project was in the best interest of the City at the time because the City had not yet received the federal funding for the project as anticipated. 

 

The project was advertised for rebid on February 12, 2020. Four (4) bids were received and opened on February 27, 2020.

This project includes 2,995 square yards of asphalt paving (1,270 linear feet), 2,564 of concrete ribbon curb, driveway replacements, storm drain pipe and structures and 278 square yards (625 linear feet) of sidewalk.

 

The attached bid tabulation shows the bids in which M. A. Smith Contracting Company, Inc. was the low bidder at $406,969.80. The estimated cost of this project was $310,249.40.

 

The funding for this project has been designated as part of the 2018-2019 Community Development Block Grant Program (CDBG) in the amount of $348,693.01; and additional funding through the general fund. With the nature of the project including the reconstruction of streets, staff is proposing using funds that were allocated in the Street Department for Street Maintenance as the offset for the additional $58,276.79.

 

Prior City Council Action

City Council approved Resolution Number 1750-20-02-11-0700 rejecting all bids received on October 3, 2019 for the 2019 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on El Malino and Bellemeade Project at the February 11, 2020 meeting.

 

Deadline for City Council Action

Action is requested on April 14, 2020

 

Funding Expected: Revenue __  Expenditure X   N/A __ 

Budgeted Item: Yes _X_ No __  N/A __ (CDBG Expenditure)                     

Amount: _$406,969.80___ 

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A __ Required __ Date Completed: _Legal will review prior to City Manager’s signature_                                          

 

Supporting documents attached:

Letter of Recommendation and Bid Tabulation

Project Map

 

Recommended Action

Approve a construction contract for the 2019 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on El Malino and Bellemeade to M.A. Smith Contracting Company, Inc., the lowest responsible bidder of four (4) bids received on February 27, 2020, in the amount of $406,969.80 and authorizing the City Manager to execute same.