Approving a professional services supplemental agreement No. 1 with Quiddity Engineering, LLC, in the amount of $557,144, associated with the Rehabilitation of Wastewater Lines, and authorizing the City Manager to execute the same.
Summary
The Rehabilitation of Wastewater Lines (WW2306) was identified in the Wastewater Master Plan as a necessary rehabilitation of the existing 30+ year old gravity wastewater lines in the Gatlinburg and Bohls Place neighborhoods. As part of Project No. WW2306 Rehabilitation of Wastewater Lines, the City desires to rehabilitate the wastewater lines within the Gatlinburg neighborhood to reduce and eliminate inflow and infiltration (I&I). The City recently completed cleaning and televising within the Gatlinburg neighborhood and identified several segments to be removed and replaced, along with manhole rehabilitation. The proposal includes professional services for final design, bidding, surveying, geotechnical, and environmental services for approximately 4,400 LF of 8”-12” sewer and 60 manholes. The project also includes cleaning and televising, and smoke testing of the Bohls neighborhood to identify defects to reduce and eliminate I&I. The proposal also includes professional services to prepare a cleaning, televising, and smoke testing bid package, solicitation, bid, coordination while services are being completed, review of results, and assembly of a preliminary engineering report recommending the types of rehabilitation needed for approximately 25,477 LF of sewers ranging in size from 6”-8”, and approximately 70 sewer manholes.
This item supports the Residential and Node Development pillar of the Strategic Plan by improving the City’s infrastructure in existing neighborhoods to serve both current and future Pflugerville residents.
Prior City Council Action
On August 13, 2024, City Council approved a Professional Services Agreement with Quiddity Engineering, LLC in the amount of $174,345 to provide professional engineering services associated with the Rehabilitation of Wastewater Lines Project.
Deadline for City Council Action
Action is requested on October 28, 2025.
Funding Expected: Revenue __ Expenditure _X_ N/A __
Budgeted Item: Yes _X_ No __ N/A __
Budget Source: Reserve fund
Amount: $557,144
1295 Form Required? Yes _X_ No __
Legal Review Required: N/A __ Required _X_ Date Completed: 10/16/2025
Supporting documents attached:
Professional Services Supplemental Agreement 1
Rehabilitation of Wastewater Lines Map
Recommended Action
Approve a Professional Services Supplemental Agreement with Quiddity Engineering, LLC. for professional engineering services associated with the Rehabilitation of Wastewater Lines, and authorizing the City Manager to execute the same.