File #: RES-1054    Version: 1 Name:
Type: Resolution Status: Consent Agenda
File created: 11/9/2022 In control: Engineering Dept
On agenda: 11/29/2022 Final action: 11/29/2022
Title: Approving a resolution authorizing the City Manager to execute an Interlocal Cooperation Agreement with Travis County regarding the placement of a pipe encasement for the City’s Secondary Colorado River Raw Water Line along Wells Branch Parkway.
Attachments: 1. Proposed Resolution, 2. Interlocal Cooperation Agreement_Raw Waterline Encasement Pipe, 3. Draft Presentation_RES-1054

Title

Approving a resolution authorizing the City Manager to execute an Interlocal Cooperation Agreement with Travis County regarding the placement of a pipe encasement for the City’s Secondary Colorado River Raw Water Line along Wells Branch Parkway.

 

Summary

This resolution is requested to approve an Interlocal Cooperation Agreement (ILA) with Travis County regarding the placement of a pipe encasement for the City’s Secondary Colorado River Raw Water Line along Wells Branch Parkway.

 

The City of Pflugerville (City) and Travis County (County) desire to continue to cooperatively construct Travis County’s Wells Branch Parkway Improvements Project and the City of Pflugerville’s Secondary River Raw Water Line Project.  Travis County is completing the design of the Wells Branch Parkway Improvements, and it was determined that the relocation of the existing City of Pflugerville’s thirty inch (30-inch) raw waterline would be required to accommodate the roadway improvements.

 

Also, the City will construct a new raw water line parallel to the existing pipeline and would require encasement at the Wells Branch Parkway crossing to protect the waterline from damage.  Further, it was determined that a costs savings could be possible if the installation of a new steel encasement by open trench for the future raw waterline was incorporated into the roadway construction project.  The project will include relocation of the existing 30-inch City of Pflugerville Raw Waterline which will be funded by Travis County.  The City of Pflugerville funded construction includes a new 30-Inch gate valve and 431 linear feet of new 66-inch steel encasement installed by open trench method.

As set forth in Exhibit B, the there is a nominal project integration cost amount for the Secondary Colorado River Raw Water Line encasement to the project estimated to be $2,860.00.  The County’s cost estimate for construction costs of the Raw Water encasement Project is $897,574.00, including $134,636.10 contingency, for an estimated total construction cost amount of $1,032,210.10.  The interlocal agreement stipulates that the City will make payment to an escrow account for the estimated costs for installation of the new valve, pipe encasement, integration and contingency costs associated with the new casing within certain timeframes.  The total financial obligation for this Interlocal Agreement is in the amount of $1,035,070.10.  

Prior City Council Action
City Council approved a professional services agreement with Freese and Nichols Inc. in the amount of $7,309,766 for professional services associated with the Secondary Colorado River Raw Water Line Project at the February 8, 2022 meeting.

City Council approved a resolution authorizing the Construction Manager-at-Risk (CMAR) project delivery method for the construction of the Secondary Colorado River Raw Water Line Project at the March 8, 2022 meeting.

City Council approved a professional services agreement with CP&Y, Inc. in the amount of $1,430,440 to provide Owner’s Representative Services associated with the Secondary Colorado River Raw Water Line project at the May 24, 2022 meeting.

City Council approved a resolution authorizing the competitive sealed proposal method for the procurement of equipment and the construction of the Secondary Colorado River Raw Water Line project at the March 8, 2022 meeting.

City Council approved a Work Authorization with CBRE in the amount of $293,700 for appraisals on 89 parcels along the Secondary Colorado River Raw Water Line Project at the October 11, 2022 meeting.

Deadline for City Council Action
Action is requested on November 29, 2022.


Funding Expected
: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes __ No __  N/A _X*_
*This agreement will be funded as part of the Secondary Colorado River Raw Water Line Project as approved in the FY23 CIP Water budget.
                     

Amount: $1,035,070.10 

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A __ Required _X_ Date Completed: _November 14, 2022_                                          

 

Supporting documents attached:

Proposed Resolution

Interlocal Cooperation Agreement_Raw Waterline Encasement Pipe

Draft Presentation

 

Recommended Action

Approve a resolution authorizing the City Manager to execute an Interlocal Cooperation Agreement with Travis County regarding the placement of a pipe encasement for the City’s Secondary Colorado River Raw Water Line along Wells Branch Parkway.