File #: 2024-0314    Version: 2 Name:
Type: Agenda Item Status: Approved
File created: 3/26/2024 In control: Engineering Dept
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Approving a professional services supplemental agreement with Freese and Nichols, Inc. in the amount of $1,982,815 for construction phase services associated with the Secondary Colorado River Raw Water Line Project and authorizing the City Manager to execute the same.
Attachments: 1. Professional Services Supplemental Agreement No 4_SCR RWL Construction Phase Services

Title

Approving a professional services supplemental agreement with Freese and Nichols, Inc. in the amount of $1,982,815 for construction phase services associated with the Secondary Colorado River Raw Water Line Project and authorizing the City Manager to execute the same.

 

Summary

This agenda item requests approval of a Professional Services Supplemental Agreement with Freese and Nichols, Inc. in the amount of $1,982,815 for construction phase services associated with the Secondary Colorado River Raw Water Line Project. This item supports the Infrastructure Pillar of the Strategic Plan.

 

The Secondary Colorado River Raw Waterline project will include improvements to the Colorado River Intake Pump Station (Package 1 and Package 2) and approximately 15 miles of 42-inch water pipeline (Packages 3 and 4), to allow for increase transfer in water supply from the Lower Colorado River Authority (LCRA). The City through a revised agreement with LCRA has increase its annual allotment from 12,000 acre-feet per year to 24,000 acre-feet per year.

 

The construction phase of this project is estimated to begin in the fall of 2024 and is expected to be complete by summer of 2026 (approximately 21 months). This is with the exception of the pump station equipment pre-purchase package (Package 1) which is currently underway and is expected to be complete by fall of 2024.

 

This Agreement provides professional construction phase services to ensure that the project construction is conducted to the standards required by the City of Pflugerville. The scope of work is based upon the assumption that one general contractor will be awarded Package 2 and one general contractor will be awarded Packages 3 and 4.

The scope of work of the agreement includes:

 

                     Project Reporting

                     Agency and Stakeholder Coordination

                     Construction Site Visits and Progress Meeting and Notes

                     Specialty Observation Site Visits

                     Monthly Construction Progress Meetings

                     Construction Coordination

                     Shop Drawings/Submittal Review

                     Alternatives and Substitutions Evaluation

                     Request for Information (RFIs)

                     Substantial/Final Completion Inspections

                     Start-up and Commissioning Assistance

                     Record Drawings

                     Easement Acquisition Services

 

Prior City Council Action
On February 12, 2022, City Council approved a Professional Services Agreement with Freese and Nichols, Inc. in the amount of $7,309,766 for design and bid phase services associated with the Secondary Colorado River Raw Water Line project.

On October 10, 2022, City Council approved a Professional Services Supplemental Agreement with Freese and Nichols, Inc. in the amount of $72,515 to provide construction phase services associated with Package 1 of the Secondary Colorado River Raw Water Line project.

Deadline for City Council Action

Action is requested on March 26, 2024

 

Funding Expected: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes _X_ No __  N/A __                      

Amount: $1,982,815

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A __ Required _X_ Date Completed: _March 18, 2024                     

 

Supporting documents attached:

Professional Services Supplemental Agreement Construction Phase Services for the Secondary Colorado River Raw Water Line Project

 

Recommended Action

Approve a professional services supplemental agreement with Freese and Nichols, Inc. in the amount of $1,982,815 for construction phase services associated with the Secondary Colorado River Raw Water Line Project, and authorize the City Manager to execute the same.