File #: 2024-0807    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 8/14/2024 In control: Public Works
On agenda: 8/27/2024 Final action: 8/27/2024
Title: Approving a work authorization with Seven Arrows Land Staff, LLC in the amount of $278,800 for right-of-way and appraisal services associated with the SH 130 Water Line Project, and authorizing the City Manager to execute the same.
Attachments: 1. Work Authorization, 2. ROW Map

Title

Approving a work authorization with Seven Arrows Land Staff, LLC in the amount of $278,800 for right-of-way and appraisal services associated with the SH 130 Water Line Project, and authorizing the City Manager to execute the same.

Summary

The proposed agenda item requests approval of a Work Authorization with Seven Arrows Land Staff, LLC. (7 Arrows)staff to provide right-of-way and appraisal services for the SH 130 Water Line Project.

On August 9, 2022, City Council approved a professional services agreement with Walker Partners, LLC., Inc. to provide design and bid phase services for the SH 130 Water Line project. The SH 130 Water Line project will provide increased water capacity, provide improved fire flow protection, promote development along the SH 45 corridor and provide a robust infrastructure to benefit the residents of the City of Pflugerville. The design phase has progressed to 30% completion, finalizing the alignment. The alignment identified seventeen (17) parcels of land within the project limits. At this time, it is critical to begin the property acquisition coordination with the effected property owners and the project team to maintain the project schedule.

The proposed work authorization includes a comprehensive list of services related to the necessary property acquisition on seventeen parcels of land for the project. The scope of work includes:

1. Obtain right-of-entries
2. Maintain administrative documents and assist with recordation of easements
3. Property record research
4. Appraisal reports
5. Owner negotiations

6.Project management

If litigation work must be completed additional services will be negotiated.

This item supports the infrastructure pillar of the Strategic Plan by expanding the City’s water capacity for present and future needs.  

 

Prior City Council Action

City Council approved a professional services agreement with Walker Partners, LLC. in the amount of $648,778 for design and bid phase services associated with the SH 130 Water Line Project at the August 9, 2022, meeting.

 

Deadline for City Council Action

Action is requested on August 27, 2024.

 

Funding Expected: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes _X_ No __  N/A __                     

Amount: ___$278,800_

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A __ Required _X_ Date Completed: _____07/23/2024__                                          

 

Supporting documents attached:
Work Authorization
ROW Map

Recommended Action

Approve a Work Authorization with Seven Arrows Land Staff, LLC in the amount of $278,800 for right-of-way and appraisal services associated with the SH 130 Water Line Project, and authorize the City Manager to execute the same. This item supports the infrastructure pillar of the City's Strategic Plan.