Title: Professional Services Agreement with Bridgefarmer & Associates, Inc. in the amount of $99,995.16 for field engineering services associated with the TR2307 Pavement Maintenance Program FY27 - Pflugerville Parkway Project.
Attachments: 1. Professional Services Agreement, 2. Project Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
Professional Services Agreement with Bridgefarmer & Associates, Inc. in the amount of $99,995.16 for field engineering services associated with the TR2307 Pavement Maintenance Program FY27 - Pflugerville Parkway Project.

 

Summary
Staff recommends approval of a Professional Services Agreement with Bridgefarmer & Associates, Inc. for field engineering services on an as-needed basis in support of the TR2307 Pavement Maintenance Program FY27 along Pflugerville Parkway.

 

On February 11, 2020, the City Council received the 2019 Pavement Report, which presented the results of an analysis of city roadway conditions. The report scored each roadway and recommended rehabilitation or preservation based on its Overall Condition Index. Through the City’s Pavement Maintenance Program, staff plans and budgets for both the rehabilitation of qualifying streets and the preservation of roadways with a satisfactory Overall Condition Index. Preserving roadways while they remain in good condition helps avoid more extensive and costly rehabilitation later. At its October 12, 2021, meeting, the City Council received a presentation outlining the Pavement Maintenance Program plan, including proposed rehabilitation and preservation projects. The program is now in its sixth year, and staff recommends approval of the planned FY27 preservation project for improvements to Pflugerville Parkway.

The proposed agreement covers approximately 12,890 linear feet of Pflugerville Parkway from 0.2 miles west of SH 130 to 0.2 miles west of N Heatherwilde Boulevard. Services include weekly coordination meetings, data collection (as-built/record plans, GIS, topographic mapping, and targeted mobile LiDAR or conventional survey of pavement, curb and gutter, sidewalks, ramps, utilities, and drainage), mill-and-overlay limits and typical sections, identification of localized pavement repairs, ADA sidewalk and ramp replacement limits with compliance grading, miscellaneous rehabilitation and traffic-control details, a stormwater pollution prevention plan, and responses to contractor RFIs and field changes. The agreement term extends through December 31, 2027, at a not-to-exceed fee of $99,995.16.

 

This item is supported by the Infrastructure pillar of the Strategic Plan.

 

Prior City Council Action

07/28/2020 approved Pavement Preservation

06/22/2021 approved Pavement Preservation

05/24/2022 approved Pavement Preservation

04/25/2023 approved Pavement Preservation

06/25/2024 approved Pavement Preservation

05/13/2025 approved Pavement Preservation

 

Deadline for City Council Action

November 10th, 2026

 

Funding Expected: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes _X_ No __  N/A __

Budget Source: _CO2023A_______                     

Budgeted Amount: __$99,995.16 _____

Amount: _$99,995.16 _______ 

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A __ Required _X_ Date Completed: _10/23/2026__                                          

 

Supporting documents attached:

Professional Services Agreement

Project Map

 

 

Recommended Action

Approve the Professional Services Agreement between City and Bridgefarmer, Inc. in the amount of 99,995.16 for field engineering services associated with the TR2307 Pavement Maintenance Program FY27 - Pflugerville Parkway project.