File #: 2025-0741    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 9/23/2025 In control: Parks and Recreation
On agenda: 9/23/2025 Final action: 9/23/2025
Title: Approving a change order in the amount of $353,256 for 1849 Park Phase 2 with G. Hyatt Construction, Inc., and authorizing the City Manager to execute the same.
Attachments: 1. Area map, 2. Change Order

Title

Approving a change order in the amount of $353,256 for 1849 Park Phase 2 with G. Hyatt Construction, Inc., and authorizing the City Manager to execute the same.

 

Summary

This item requests approval of a change order with G. Hyatt Construction, Inc. in the amount of $353,256 and an extension of 48 contract days. The change order reflects scope adjustments required by Oncor.

 

The scope adjustments include modification of the primary electrical conduit run, approximately 1,000 linear feet, from the existing transformer near the football fields to the new transformer pad under construction near the baseball fields, along with the installation of an additional 2,353 linear feet of primary underground electrical conduit. This new conduit run, as required by Oncor, will create a loop within 1849 Park. A looped circuit improves system reliability by providing redundant power pathways, reducing the likelihood of outages, and allowing maintenance or repairs to occur without disrupting service to the entire park. The change order also includes the necessary conduit, excavation, bedding material and backfill, boring, junction boxes, an electrical riser, fine grading, and seeding.

 

These changes have been evaluated for their impact on the project schedule, budget, and overall feasibility. Approval of this change order will increase the construction contract total to $9,535,563, reflecting a 3.8% increase to the previously approved contract amount.

 

Once the new electrical line has been installed, staff will bring forward an easement request for City Council consideration to formalize Oncor’s access and maintenance rights.

 

With the added contract extension, substantial completion is now scheduled for December 22, 2025, with final completion on January 21, 2026.

 

The overall construction budget, which includes contingency for unforeseen conditions, is adequate to accommodate this adjustment without the need for additional funding.

 

This item is supported by the {Safety/Infrastructure/Economic Development/Services} pillar of the Strategic Plan.

 

Prior City Council Action

On September 10, 2024, City Council approved a construction contract with G Hyatt Construction, LLC. in the amount of $8,901,547.

On April 8, 2025, City Council approved a change order for $144,739 with G Hyatt Construction, Inc. The change was for the purchase and installation of a Tuff Shed for maintenance operations and additional pedestrian safety railings.

On August 26, 2025, City Council approved a change order for $77,664 for ADA-related improvements.

Deadline for City Council Action

Action is requested on September 23, 2025.

 

Funding Expected: Revenue __  Expenditure X_  N/A __ 

Budgeted Item: Yes X_ No __  N/A __

Budget Source: _2020 GO Bond_                     

Amount: _$353,256

1295 Form Required? Yes __ No X_                     

Legal Review Required: N/A X_ Required __ Date Completed: ___________                                          

 

Supporting documents attached:

Change Order

Area Map

 

Recommended Action

Approve the change order in the amount of $353,256 for 1849 Park Phase 2 with G. Hyatt Construction, Inc.