File #: 2024-1144    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 11/14/2024 In control: Public Works
On agenda: 11/26/2024 Final action: 11/26/2024
Title: Approving a Facility Extension Agreement with Oncor Electric Delivery to provide a construction power to the Wilbarger Creek Regional Wastewater Treatment Facility in the amount of $52,381, and authorizing the City Manager to execute the same.
Attachments: 1. Oncor Facility Extension Agreement

Title

Approving a Facility Extension Agreement with Oncor Electric Delivery to provide a construction power to the Wilbarger Creek Regional Wastewater Treatment Facility in the amount of $52,381, and authorizing the City Manager to execute the same.

 

Summary

As part of the Wilbarger Creek Regional Wastewater Treatment Facility construction, temporary power is required to both the office trailers for the construction management team and for a portion of the site under construction.  These two locations within the property boundaries allow for streamlined construction activities to take place across the site to allow for an efficient operation of the City’s largest capital improvement project. 

 

The City has already contracted with Oncor for the first set of temporary power connections to be made on-site for the construction management team and staff have been coordinating with Oncor on the exact equipment and locations where the second phase of construction power is needed on the site.  After performing limited survey work and confirming there would not be any conflicts with Oncor’s proposed route to provide power to the northern portion of the site, Oncor developed a Facility Extension Agreement to provide power to the northern portion of the site that is currently undergoing construction. 

 

While this extension of electrical equipment could be covered under the contractor Construction Manager At Risk (CMAR) contract, staff elected early in the process to have all coordination with Oncor and the cost for power to the site be contracted directly with the City instead of the CMAR.  While this requires a small amount of coordination and effort by the City to accomplish this, it also eliminates the need for the City to pay the CMAR fee of 9% on extending the electrical equipment per the CMAR contract. 

 

This agreement meets the City’s strategic goal of infrastructure by ensuring the construction of the Wilbarger Creek Regional Wastewater Treatment Facility can continue to be constructed efficiently to provide resilient wastewater services for the City of Pflugerville.

 

Prior City Council Action

On February 11, 2020, City Council approved a Professional Services Agreement with CP&Y, Inc. in the amount of $479,944 for Owner’s Representative services associated with the Wilbarger Creek Regional Wastewater Treatment Facility.

On September 22, 2020, Council approved selection of Garver for professional services associated with the Wilbarger Creek Regional Wastewater Treatment Facility Project.

On October 27, 2020, Council approved a professional services agreement in the amount of $1,650,192 with Garver for the conceptual design of the Wilbarger Creek Regional Wastewater Treatment Facility Project.

 

On June 22, 2021, Council approved a professional services supplemental agreement with CP&Y, Inc. in the amount of $1,407,592 for Owner’s Representative services for preliminary design, final design and bid phase services for the Wilbarger Creek Regional Wastewater Treatment Facility Project.

 

On June 22, 2021, Council approved a professional services supplemental agreement with Garver in the amount of $7,896,181 for preliminary design, final design and bid phase services for the Wilbarger Creek Regional Wastewater Treatment Facility Project.

 

On July 12th, 2022, Council approved a resolution authorizing the use of the Competitive Sealed Proposal (CSP) procurement method for the Wilbarger Creek Regional Wastewater Treatment Facility (WCRWWTF) Project, including the Pre-Selection of vendors for major treatment process equipment.

 

On September 27th, 2022, City Council awarded a pre-procurement contract to Trojan Technologies for the supply of UV Disinfection Equipment for the WCRWWTF in the amount of $655,520.

 

On January 10th, 2022, City Council awarded a pre-procurement contract to T. Morales Company Electrical and Controls, Ltd. to supply Electrical Equipment for the WCRWWTF in the amount of $7,106,645.

 

On March 14, 2023, City Council awarded a pre-procurement contract with Alterman, Inc. to supply Generator Equipment for the WCRWWTF in the amount of $1,667,229.

 

On March 14, 2023, City Council awarded a professional services supplemental agreement with CP&Y, Inc. in the amount of  $2,187,985 to provide Owner's Representative Pre-Construction Construction Phase Services for the Wilbarger Regional Wastewater Treatment Facility.

 

On April 14, 2023, City Council awarded a Construction Manager at Risk contract with PLW Waterworks, LLC. in the amount of $1,502,344 for the Construction Manager at Risk - Wilbarger Creek Regional Wastewater Treatment Facility (WCRWWTF) Project Phase 1 Construction.

 

On November 14, 2023, City Council awarded the GMP # 1 Package to PLW Waterworks, LLC. in the amount of $35,492,185 for construction services associated with the Wilbarger Creek Regional Wastewater Treatment Facility.

 

On June 11, 2024, City Council awarded the GMP # 2 Package to PLW Waterworks, LLC. in the amount of $201,902,913 for construction services associated with the Wilbarger Creek Regional Wastewater Treatment Facility.

 

Deadline for City Council Action

November 26, 2024

 

Funding Expected: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes _X__ No __  N/A __                                          

Amount: _$52,381_______ 

1295 Form Required? Yes __ No _X_                     

Legal Review Required: N/A _X_ Required ___ Date Completed: _______                                          

 

Supporting documents attached:

Oncor Facility Extension Agreement

 

Recommended Action

Staff recommends authorizing the City Manager to execute a Facility Extension Agreement with Oncor Electric Delivery for the Wilbarger Creek Regional Wastewater Treatment Facility in the amount of $52,381.