File #: 2023-1103    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 11/2/2023 In control: Public Works
On agenda: 11/14/2023 Final action: 11/14/2023
Title: Discuss and consider action to approve a construction contract with PLW Waterworks in the amount of $35,492,185 for construction services associated with the Wilbarger Creek Regional Wastewater Treatment Facility, and authorize the City Manager to execute the same.
Attachments: 1. Total Project Estimate - November 2023, 2. GMP # 1 Letter of Recommendation, 3. GMP # 1 Bid Documents
Title
Discuss and consider action to approve a construction contract with PLW Waterworks in the amount of $35,492,185 for construction services associated with the Wilbarger Creek Regional Wastewater Treatment Facility, and authorize the City Manager to execute the same.

Summary
The Wilbarger Creek Regional Wastewater Treatment Facility (WCRWWTF) phase 1 Project will expand water resources to maintain the highest level of service and quality of life to City of Pflugerville residents with the construction of a 6.0 MGD wastewater treatment plant on a 158-acre site and decommissioning of the existing Weiss Lane Lift Station. Design of the project began in November 2020 with the award of the Garver contract and was completed in December 2022. In September 2022, January 2023, and March 2023, Council approved early procurement of long lead equipment. In May 2023, Council Awarded the Pre-Construction Services Contract for the Construction Manager At Risk (CMAR) to PLW Waterworks (PLW).

The current CMAR contract with PLW includes Pre-Construction Services in the amount of $1,502,344 covering the activities conducted for design optimization, constructability reviews and cost estimating for the entire project. Working with the CMAR, the City of Pflugerville Team (City Team) consisting of City staff, Garver - Engineer of Record (EOR), STV - City’s Owner’s Advisor (OA), and Ardurra - City’s Construction Management Consultant (CM) determined that the optimal strategy to move the project forward as efficiently as possible without disrupting the Guaranteed Maximum Price (GMP) Proposal process was the development of several Early Work Packages (EWPs) and separate the GMP into two deliverables.

- GMP1 - Early Work Packages
- GMP2 - Balance of Plant Packages

GMP1 for the EWPs is presented here for consideration and award as Amendment 1 to the CMAR contract for construction of the WCRWWTF. The cost of EWPs will be a component of the overall project GMP and not in addition ...

Click here for full text