Title
Approving a contract with Patin Construction, LLC. in the amount of $312,733 for construction associated with the Heatherwilde/Cheyenne Drainage improvements project, and authorizing the City Manager to execute the same.
Summary
During routine maintenance, Streets and Drainage staff members discovered deterioration of a storm manhole in need of repair located at the intersection of Heatherwilde Boulevard and Cheyenne. Staff then went had the manhole inspected in order to determine the immediate threat to infrastructure as well as the plan and extent of repair.
Engineering for the required repair was performed in FY22 while staff maintained the condition of the manhole. Funding was approved for construction as part of the FY23 approved budget.
Prior City Council Action
N/A
Deadline for City Council Action
January 10, 2023
Funding Expected: Revenue __ Expenditure _X_ N/A __
Budgeted Item: Yes _X_ No __ N/A __
Amount: $312,733
1295 Form Required? Yes _X_ No __
Legal Review Required: N/A __ Required _X_ Date Completed: __12-28-2022__
Supporting documents attached:
Cheyenne Recommendation Letter
Heatherwilde-Cheyenne Storm Rehabilitation Agreement
Recommended Action
Approve a contract with Patin Construction, LLC. in the amount of $312,733 for construction associated with the Heatherwilde/Cheyenne Drainage improvements project and authorizing the City Manager to execute the same.