File #: 2022-1013    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 10/13/2022 In control: Engineering Dept
On agenda: 10/25/2022 Final action: 10/25/2022
Title: Approving a construction contract with Dan Williams Company, in the amount of $1,002,396 associated with the Rowe Lane at FM 685 Project, and authorizing the City Manager to execute the same.
Attachments: 1. Pape-Dawson Letter of Recommendation, 2. Draft Presentation_2022-1013
Title
Approving a construction contract with Dan Williams Company, in the amount of $1,002,396 associated with the Rowe Lane at FM 685 Project, and authorizing the City Manager to execute the same.

Summary
This agenda item is a request for City Council approval for awarding a construction contract related to the Rowe Lane at FM 685 intersection improvements project (Project). This item supports the Infrastructure pillar of the Strategic Plan.

The design effort for the intersection improvements of Rowe Lane at FM 685 were initiated in July 2019, as a result of two Traffic Impact Analysis (TIA) reports that were conducted (2015 and 2019).The Project is funded by the 2018 Certificate of Obligation Bond Program. The purpose of the Project is to reduce congestion and increase safety at the intersection. The Project consists of the addition of deceleration and acceleration lanes at Rowe Lane while maintaining two through lanes on FM 685.

Advertisement for the Project began on September 14, 2022, in the Pflugerville Pflag as required. The City of Pflugerville opened the four (4) bids received for the project on October 5, 2022, at 2:00 p.m. Dan Williams Company is the recommended lowest responsible bidder. During the bid evaluation, the Engineer performed a reference check and coordinated with TxDOT and received concurrence to award the construction contract.

A Notice to Proceed is anticipated in November 2022, and construction duration is approximately 60 days.

Background
Two Traffic Impact Analysis (TIA) reports were conducted in 2015 and 2019. Both TIA reports show an increase of right turning volumes departing Rowe Lane onto FM 685. The TIA reports support the addition of acceleration/deceleration lanes at this intersection due to the high number of right turns onto and from Rowe Lane. Also, proposed improvements maintain consistency with the City of Pflugerville requirement for acceleration/deceleration lanes where right turn volume exceeds 50 vehicles du...