File #: 2022-0716    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 7/15/2022 In control: Engineering Dept
On agenda: 7/26/2022 Final action: 7/26/2022
Title: Approving a professional services supplemental agreement with Halff Associates, Inc. in the amount of $175,159 for bid and construction phase services associated with the Historic Colored Addition Subdivision Streets: Russell Street, Caldwells Lane, Taylor Street, Grant Street and Lincoln Avenue project and authorizing the City Manager to execute same.
Attachments: 1. Professional Services Supplemental Agreement_ Halff HCA, 2. Draft Presentation_2022-0716
Title
Approving a professional services supplemental agreement with Halff Associates, Inc. in the amount of $175,159 for bid and construction phase services associated with the Historic Colored Addition Subdivision Streets: Russell Street, Caldwells Lane, Taylor Street, Grant Street and Lincoln Avenue project and authorizing the City Manager to execute same.

Summary
This agenda item is for Halff Associates to provide bidding and construction phase services for the Historic Colored Addition Project.

On February 25, 2020, City Council approved a Professional Services Agreement with Halff Associates to move forward with the infrastructure improvements identified in the Infrastructure and Land Use Study of the Historic Colored Addition Subdivision approved in April 2019. The agreement included a full set of Plans, Specifications, and Estimate (PS&E) for constructing new and upgrading existing streets, utilities, and drainage in the subdivision as recommended. Bid and construction phase services were not included in the original agreement as funding had not yet been identified. The construction funding was recommended and approved through the 2020 General Obligation Bond.

Project design is complete, the project will bid upon completion of right-of-way acquisition and utility coordination and relocations. As part of this agreement Halff will provide continued utility coordination services, bid and construction phase services and construction materials testing.

If right-of-way and utility coordination is completed in August as anticipated, the project bid Package is planned to be ready August 2022, Bid Phase August 2022 to September 2022, Construction Award October 2022. Construction is anticipated to take eighteen (18) months.

This item is supported by the Infrastructure pillar of the Strategic Plan

Prior City Council Action
City Council approved Resolution Number 1693-19-04-09-0600 regarding the Infrastructure and Land Use Study associated with the Pfluger...