Title: Professional services supplemental agreement with LJA Engineering, Inc. in the amount of $18,763 for the Intersection Improvements at Pflugerville Pkwy and Mammoth Cave/Railroad Ave associated with TR2302 - Traffic Signal System Improvement Implementation - Transportation Alternatives Set-Aside (TASA) ADA Project.
Attachments: 1. Professional Services Supplemental Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Professional services supplemental agreement with LJA Engineering, Inc. in the amount of $18,763 for the Intersection Improvements at Pflugerville Pkwy and Mammoth Cave/Railroad Ave associated with TR2302 - Traffic Signal System Improvement Implementation - Transportation Alternatives Set-Aside (TASA) ADA Project.

Summary
The City is considering approval of Professional Services Supplemental Agreement No. 4 (PSSA) with LJA Engineering, Inc. in the amount of $18,762.40 to provide additional engineering and design services for intersection improvements at Pflugerville Parkway and Mammoth Cave/Railroad Avenue associated with the Traffic Signal System Improvement Implementation Project.

The original Professional Services Agreement was executed on September 29, 2022, in the amount of $258,460.00. Subsequent supplemental agreements provided additional traffic signal timing, engineering, bid, and construction phase services to support implementation of the project.

This Supplemental Agreement includes project management, coordination, quality assurance and quality control (QA/QC), and the preparation of Plans, Specifications, and Estimates (PS&E) for the proposed intersection improvements. The scope includes evaluating alternative curb return radii and intersection geometry using Auto-Turn analysis, field measurements and evaluation of existing elevations, and design of the selected alternative. Improvements will include modifications to corner radii and ADA-compliant curb ramps. The consultant will also prepare construction quantity summaries, cost estimates, final construction documents, and record/as-built drawings.

The supplemental agreement increases the total contract amount from $439,586.32 to $458,348.72. The project is still within the total amount originally budgeted for the overall project, and the $18,763 will come from 2023A bond funds. Approval will allow LJA Engineering, Inc. to advance the design of the intersection improvements and provide th...