File #: 2022-0138    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 2/8/2022 In control: Pflugerville Community Development Corporation (PCDC)
On agenda: 2/8/2022 Final action: 2/8/2022
Title: Approving a PCDC contract for engineering and design services in the One Thirty Business Park with DCS Engineering, in an amount not to exceed $169,500, for the purposes of extending Impact Way in the One Thirty Business Park to include Phase III-A and Phase III-B and providing administrative services for a specific use permit related to light industrial use for PCDC's 24-acre tract, and authorize the PCDC Executive Director to execute the same.
Attachments: 1. DCS agreement with PCDC 2022.01.19, 2. Updated_2022.02.08 - PCDC Impact Way Extension Phase III A & B CA CM Presentation (2)
Title
Approving a PCDC contract for engineering and design services in the One Thirty Business Park with DCS Engineering, in an amount not to exceed $169,500, for the purposes of extending Impact Way in the One Thirty Business Park to include Phase III-A and Phase III-B and providing administrative services for a specific use permit related to light industrial use for PCDC's 24-acre tract, and authorize the PCDC Executive Director to execute the same.

Summary
On January 19, 2022, the PCDC Board of Directors unanimously voted to approve an engineering and design services contract between the PCDC and DCS Engineering for
continuation of the build out of Impact Way in the SH-130 Commerce Center located at the southwestern corner of E. Pecan St. and SH-130. The board is forwarding the Contract to the City Council for review and consideration. The Commerce Center has been constructed in multiple phases; a summary of each phase is described below:

1. Phase I: Phase I of the SH-130 Commerce Center began design in 2011 and constructed Helios Way as well as the intersection of Impact Way and E. Pecan St. The construction for this project was completed in 2013.

2. Phase II: The Phase II project-built Impact Way from the Intersection at E. Pecan St. to the south, stopping just north of the regional detention pond. The project began design in 2013 and construction was completed in 2014.

3. Phase III: The Phase III-A project began design in June 2017 and consists of a 560 ft long extension of Impact Way to the South. In May 2018, The PCDC and City of Pflugerville signed a Memorandum of Understanding stating that the plat would be recorded prior to construction of the public improvements. This project was reviewed by the City and administratively approved prior to being placed on hold in August 2018 for financial considerations. In December 2020, the project resumed the process of obtaining final City approval. As of November 2021, the construction plans for Phase III-A...