Title
Discuss and consider action to approve the procurement of two influent lift station pumps for the Central Wastewater Treatment Plant in the amount of $143,000, and authorize the City Manager to execute the same.
Summary
This item is for the procurement of two replacement influent lift station pumps for the Central Wastewater Treatment Plant. The influent lift station pumps are critical process equipment needed to maintain flow into the treatment plant.
This item is supported by the Residential and Node Development and Economic and Business Development pillars of the Strategic Plan by maintaining infrastructure in a safe and resilient manner.
Prior City Council Action
No prior city council action related to this item.
Deadline for City Council Action
Action requested by July 14, 2026
Funding Expected: Revenue __ Expenditure _X_ N/A __
Budgeted Item: Yes _X_ No __ N/A __
Budget Source: Capital Outlay operating budget
Budgeted Amount: _$143,000 (from savings of other equipment that came under budgeted amount)
Amount: _$143,000__
1295 Form Required? Yes __ No _X_
Legal Review Required: N/A _X_ Required __ Date Completed: ___________
Supporting documents attached:
Zone Industries Pumps_Quote
Recommended Action
Staff recommends approving the procurement two influent lift station pumps for the Central Wastewater Treatment Plant in the amount of $143,000 and authorize the City Manager to execute the same.