File #: 2023-0926    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 9/27/2023 In control: Engineering Dept
On agenda: 10/10/2023 Final action: 10/10/2023
Title: Approving a professional services supplemental agreement with Burns and McDonnell Engineering Company, Inc, in the amount of $204,313.39 for professional engineering services associated with the 2020 Transportation Bond Program Project; Intersection Improvements II (E. Pflugerville Parkway at FM 685 and Copper Mine Overpass - SH 130 at FM 685), and authorizing the City Manager to execute same.
Attachments: 1. Professional Services Supplemental Agreement
Title
Approving a professional services supplemental agreement with Burns and McDonnell Engineering Company, Inc, in the amount of $204,313.39 for professional engineering services associated with the 2020 Transportation Bond Program Project; Intersection Improvements II (E. Pflugerville Parkway at FM 685 and Copper Mine Overpass - SH 130 at FM 685), and authorizing the City Manager to execute same.

Summary
On July 27, 2021, the City Council approved a Professional Services Agreement (PSA) with Burns and McDonnell Engineering Company, Inc. (BMD) for the engineering design of the Intersection Improvements II (E. Pflugerville Parkway at FM 685 and Copper Mine Overpass - SH 130 at FM 685). This Project supports the infrastructure pillar of the strategic plan.

On September 13, 2022, the City Council approved Supplement #1 to the PSA with BMD, including final engineering design and analysis and construction phase services for the improvements to the intersections of SH130 (Copper Mine Overpass) and FM 685 and E. Pflugerville Parkway and FM 685.

On May 9, 2023, the City and BMD executed Supplemental #2 to the PSA to reallocate fees, specifically funds from BMD sub-consultants to BMD. No additional Project funding was in this supplemental agreement.
At the city's request, BMD has prepared Supplement #3 to the PSA for professional services to complete the preparation of the final engineering design and analysis of the improvements to the intersections of E. Pflugerville Parkway at FM 685 and Copper Mine at SH 130. Additional service as follows:
· A Traffic Analysis of the impacts and configuration of the improvements on E. Pflugerville Parkway and FM 685.
· Redesign the improvements along FM 685 for the Copper Mine intersection, reducing the southbound lanes to 11’.
· Develop multiple design ideas and exhibits that reflect the changes after the approved Schematic.
· Attend additional meetings with developers, City staff, GEC, TxDOT, and ROW acquisition staff.
...