File #: 2026-0297    Version: 1 Name:
Type: Agenda Item Status: Consent Agenda
File created: 3/10/2026 In control: Public Works
On agenda: 3/24/2026 Final action:
Title: Conditional purchase agreement and associated conveyance documents between Lakeside Water Control and Improvement District No. 2D (Parcels 21, 23 & 25) and the City of Pflugerville as necessary to acquire real property interests for the Kelly Lane Phase 3 Project.
Attachments: 1. Purchase Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Conditional purchase agreement and associated conveyance documents between Lakeside Water Control and Improvement District No. 2D (Parcels 21, 23 & 25) and the City of Pflugerville as necessary to acquire real property interests for the Kelly Lane Phase 3 Project.

Summary
This agenda item requests approval of a conditional purchase agreement and associated conveyance documents between Lakeside Water Control and Improvement District No. 2D (Parcels 21, 23 & 25) and the City of Pflugerville as necessary to acquire real property interests for the Kelly Lane Phase 3 Project and authorize the City Manager to execute the same. The purpose of the project is to expand the roadway to a four-lane configuration with a center median and integrate four roundabouts intersections from Moorlynch Avenue to Weiss Lane. Additionally, construction encompasses curb and gutter, underground storm facilities, pedestrian enhancements, and street lighting.

This purchase agreement with Lakeside Water Control and Improvements District No. 2D in the amount of $500,000 was negotiated to obtain the necessary right-of-way and a utility easement to construct the project and is subject to City Council approval.

This project supports the Mobility infrastructure and connectivity Pillar of the Strategic Plan.


Prior City Council Action
City Approved selection of Vickrey and Associates, LLC for professional engineering services associated with the 2020 Transportation Bond Program Project: Kelly Lane Phase 3 and authorizing the City Manager to execute a professional services agreement in the amount of $1,527,103.59 on July 27, 2021.

City Council approved to take action and authorize City Staff and City Attorney to take any and all action necessary to secure right-of-entry and access to real property for the purpose of conducting a survey and any other testing as needed for the Kelly Lane phase 3 project on February 8, 2022.

City Council approved a Professional Services Supplemental Agree...