Title: Approving a Professional Service Agreement with Collier Consulting in the amount of $89,876.40 for professional engineering services associated with the Well 6 Water Supply Evaluation Project, and authorizing the City Manager to execute the same.
Attachments: 1. Professional Services Agreement_Collier Well 6 Project, 2. Draft Presentation_2022-0298

Title

Approving a Professional Service Agreement with Collier Consulting in the amount of $89,876.40 for professional engineering services associated with the Well 6 Water Supply Evaluation Project, and authorizing the City Manager to execute the same. 

 

Summary

This Professional Services Agreement (PSA) is to perform preliminary engineering services to evaluate the ability for the City to expand the groundwater supplies that we have at Well # 6 that is located off of Glen Rose Chase Drive. The preliminary engineering will evaluate the feasibility to expand the groundwater well to become more drought-resistant and able to provide a more firm capacity in future years.  The evaluation will be to produce a Preliminary Engineering Report (PER) for feasibility of the project and to provide construction costs if necessary. As Well # 6 is a very large production well, by making the well more drought-resistant, it allows for the City’s water supplies to be more robust during long drought seasons and minimizes the reliance on the surface water supplies from LCRA.  This item was included within the Utility Administration budget and is labeled as “Well 6 Expansion Water Evaluation.”

 

Prior City Council Action

NA

Deadline for City Council Action

Action is requested on April 12, 2022

 

Funding Expected: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes _X_ No __  N/A __                     

Amount: _$89,876.40

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A __ Required _X_ Date Completed: __XX___                                          

 

Supporting documents attached:

Professional Services Agreement

 

Recommended Action

City staff recommends authorizing the City Manager to approve a Professional Service Agreement with Collier Consulting in the amount of $89,876.40 for professional engineering services associated with the Well 6 Water Supply Evaluation Project.