Title
Authorizing the City Manager to execute Change Order #7 with Cash Construction Co, Inc. for SH130/Kelly Lane turn lane additions as part of the Kelly Lane widening roadway Capital Improvement Project in the amount of $135,881.40.
Summary
The Kelly Lane construction contract was executed on November 13, 2013. Staff requested a change in scope to include a new east bound dedicated left turn lane at the SH130/Kelly Lane intersection. Included in Change Order #7 are additional quantities necessary for the turn lane addition and include asphalt, demolition, concrete, striping and traffic signal modifications. Additional time added to the project as a result of Change Order #7 is 98 days. The large amount of time is primarily due to ordering and receipt of traffic signal poles and mast arms. Actual construction of the turn lane should take approximately 14 days.
Deadline for City Council Action
None
Projected Future City Council Action
None
Fiscal Impact
Funding for the additional Kelly Lane improvements is from previously issued certificates of obligation for road and street projects.
Staff Recommendation
Authorize the City Manager to execute change order #7 with Cash Construction Co., Inc.
Drafter
Dan Franz, P.E.
City Engineer