Title
Discuss and consider action to approve a supplemental agreement #1 with K. Friese & Associates, Inc. in the amount of $299,430 for professional engineering services associated with design, bidding and construction administration of the Carmel Interceptor Phase 1 Project and authorizing the City Manager to execute the agreement.
Summary
The Carmel Interceptor Phase 1 project will convey wastewater flows from the new PISD high school on Weiss Lane to the new Carmel/Sorento Lift Station The project will need to be complete and in service by the middle of 2017 to meet testing requirements. This work is being added to the existing K. Friese & Associates contract to design the Carmel/Sorento Lift Station.
Preparation of the final engineering construction documents shall include but not be limited to: project design, topographic surveys, geotechnical investigation, environmental assessment and environmental clearances, identification of utility conflicts, required utility adjustments and replacements, determination of ROW/easement acquisition, preparation of ROW/easement acquisition metes/bounds and sketch, preliminary and final engineer’s opinion of probable construction cost, project manual and any other items necessary to successfully construct this project.
This project will be designed in accordance with the City of Pflugerville’s 2014 Edition of the Uniform Development Code and 2014 Edition of the Engineering Design Guidelines & Construction Manual.
The attached agreement has been reviewed and approved as to form by the City Attorney.
Status
City staff has negotiated with K. Friese & Asssociates to establish a scope of services, schedule and fee for this supplemental agreement.
Prior City Council Action
K. Friese & Associates, Inc. was selected as the Engineering Consultant for this project during the City Council meeting on July 9, 2013. A professional engineering services contract was presented to Council and approved on September 24, 2013.
Fiscal Im...