Title
Approving a professional services agreement with Quiddity Engineering, LLC in the amount of $174,345 to provide professional engineering services associated with the Rehabilitation of Wastewater Lines Project, and authorizing the City Manager to execute the same.
Summary
The Rehabilitation of Wastewater Lines (No. WW2306) is included in the 2024 Capital Improvement Program. The project will rehabilitate the wastewater lines along Great Basin Avenue and within the Gatlinburg neighborhood. The gravity sewers are predominantly PVC pipe, in excess of 30 years old, and have significant issues with both inflow and infiltration (I&I). Included are professional services to prepare a cleaning, televising, and smoke testing bid package, solicitation, proposal, coordination while services are being completed, review of results, and assembly of a preliminary engineering report with recommendation of rehabilitation methods required for approximately 25,792 LF of sewers ranging in size from 6”-24”, and approximately 80 sewer manholes. This item supports the infrastructure pillar of the City’s Strategic Plan and Comprehensive.
Prior City Council Action
N/A
Deadline for City Council Action
August 13, 2024.
Funding Expected: Revenue __ Expenditure _X_ N/A __
Budgeted Item: Yes _X_ No __ N/A __
Amount: _$174,345.00____
1295 Form Required? Yes _X_ No __
Legal Review Required: N/A __ Required _X_ Date Completed: _07/29/2024__
Supporting documents attached:
Professional Services Agreement
Recommended Action
Approve a professional services agreement with Quiddity Engineering, LLC. In the amount of $174,345 and authorize the City Manager to execute the same.