Skip to main content
Pflugerville Banner
File #: 2015-4403    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 10/29/2015 In control: Public Works
On agenda: 11/10/2015 Final action: 11/10/2015
Title: Discuss and consider action to award a construction contract for the Sorento/Carmel Lift Station project to Aaron Concrete Contractors, LP, the lowest responsible bidder of six (6) bids received on October 28, 2015, in the amount of $2,407,994.00.
Attachments: 1. Bidders List - Carmel Sorento Lift Station, 2. CS Bid Reccomendation

Title

Discuss and consider action to award a construction contract for the Sorento/Carmel Lift Station project to Aaron Concrete Contractors, LP, the lowest responsible bidder of six (6) bids received on October 28, 2015, in the amount of $2,407,994.00.

 

Summary

This project will construct a new regional lift station to service development in the Wilbarger Creek basin.

 

The construction of the new high school requires that this project must be in service by December 2016.

 

The attached bid tabulation includes the bid values in which the low bidder was $2,407,994.00. The bid received is within the estimated budget.

 

Status

The project was advertised for bids on September 23, 2015.  Six (6) bids were received and opened on October 28, 2015.

 

Fiscal Impact

Funding for this project is from wastewater impact fees and is included in the Utility Capital Improvement Plan.

Staff Recommendation

Staff recommends awarding the construction contract for the Sorento/Carmel Lift Station project to the lowest responsible bidder, Aaron Concrete Contractors, LP, in the amount of $2,407,994.00.

Drafter
Tom Word
Assistant City Manager