Pflugerville Banner
File #: 2016-5284    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 10/14/2016 In control: Public Works
On agenda: 10/25/2016 Final action: 10/25/2016
Title: Discuss and consider action to award a construction contract for the 1849 Park to Patin Construction Company, Inc., the lowest responsible bidder of six (6) bids received on October 13, 2016, in the amount of $3,028,911.45 and authorizing the City Manager to execute same.
Attachments: 1. Contractor Selection Letter, 2. Bid Tab Results List, 3. 1849 Park Phase 1 (Option B) Map

Title

Discuss and consider action to award a construction contract for the 1849 Park to Patin Construction Company, Inc., the lowest responsible bidder of six (6) bids received on October 13, 2016, in the amount of $3,028,911.45 and authorizing the City Manager to execute same.

 

Summary

This project includes the earthwork, storm drain system, water lines, landscaping and irrigation system associated with the construction of six (6) multi-purpose fields and three (3) football fields.

 

Schrickel, Rollins & Associates, the project’s design consultant, completed design work for this project in September.

 

The attached bid tabulation shows the bids in which the low bidder was $2,975,085.45. Including the accepted alternates for six feet fencing and gates results in a total of $3,028,911.45.  The estimated cost of this project was $3,800,000.

 

Mean average for the base bids was $3,543,781.48.

 

Status

The project was advertised for bids on September 28, 2016.  Six (6) bids were received and opened on October 13, 2016.

 

Fiscal Impact

Funding for this project was included in the 2014 General Obligation Bonds.

Staff Recommendation

Staff recommends awarding the construction contract for the 1849 Park project to the lowest responsible bidder, Patin Construction Company, Inc., in the amount of $3,028,911.45.

Drafter
Tom Word
Assistant City Manager