File #: 2018-6798    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 5/10/2018 In control: Public Works
On agenda: 5/22/2018 Final action: 5/22/2018
Title: Discuss and consider action to award a construction contract for the 2018 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on Mill Creek Rd. and Green Meadows St. to Smith Contracting Company, the lowest responsible bidder of six (6) bids received on May 10, 2018, in the amount of $545,038.00 and authorizing the City Manager to execute same.
Attachments: 1. 2018 CBDG_Bid Award Recommendation, 2. CDBG Pavement Rehab Map

Title

Discuss and consider action to award a construction contract for the 2018 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on Mill Creek Rd. and Green Meadows St. to Smith Contracting Company, the lowest responsible bidder of six (6) bids received on May 10, 2018, in the amount of $545,038.00 and authorizing the City Manager to execute same.

 

Summary

This project includes 4,760 square yards of paving, concrete curb and gutter, concrete ribbon curb, driveway replacements, storm drain pipe and structures and valve and manhole adjustments.

 

Dannenbaum Engineering, the project’s design consultant, completed design work for this project in April 2018.

 

The attached bid tabulation shows the bids in which Smith Contracting Company was the low bidder at $545,038.00. The estimated cost of this project was $515,538.

 

Status

The project was advertised for bids on April 25, 2018.  Six (6) bids were received and opened on May 10, 2018.

 

Fiscal Impact

The funding for this project has been designated as part of the 2014-2017 Community Development Block Grant Program (CDBG) in the amount of $497,136.58; and additional funding through the general fund.  Staff is proposing using funds that were allocated in the Administration Department for Wayfinding in the amount of $75,000, as the offset for the additional $47,901.42.  A budget amendment will be prepared for Council's consideration at the June 12 meeting.

Staff Recommendation
Staff recommends awarding the construction contract for the 2018 Community Development Block Grant (CDBG) Pavement Rehabilitation Project on Mill Creek Rd. and Green Meadows St. to the lowest responsible bidder, Smith Contracting Company, in the amount of $545,038.00.

Drafter
Amy Giannini
City Engineer

Emily Barron, AICP
Planning Director