Pflugerville Banner
File #: 2020-8746    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 10/15/2020 In control: Engineering Dept
On agenda: 10/27/2020 Final action: 10/27/2020
Title: Approving an agreement with Kimley-Horn and Associates in the amount of $69,994.20 for professional engineering services associated with the design, bidding, construction administration, and material testing for the Grand Avenue Parkway Pavement Repair Project and authorizing the City Manager to execute the same.
Attachments: 1. KH PSA _Grand Ave, 2. Project Location Map_Grand Ave., 3. Project Schedule.Grand Avenue.docx, 4. Draft Presentation_2020-8746

Title

Approving an agreement with Kimley-Horn and Associates in the amount of $69,994.20 for professional engineering services associated with the design, bidding, construction administration, and material testing for the Grand Avenue Parkway Pavement Repair Project and authorizing the City Manager to execute the same.

 

Summary

This agenda item is a follow up to the October 13th City Council approval for selection of Kimley-Horn and Associates (KHA) to provide professional engineering services associated with the 2020-2022 Pavement and Infrastructure Maintenance Projects. Specifically, staff recommends KHA to provide design, bidding and construction administration services related to the Grand Avenue Repair project. 

 

The proposed design services will be provided in a two-phase approach for engineering services with the first phase to include a Comprehensive Pavement Assessment and Repair Geotechnical Report prior to design and development of the plans, specifications and estimate (PS&E) for Grand Avenue. Phase 1, as proposed for the initial professional services agreement will provide a full evaluation analysis for an assessment of the current condition and determination for repairs along Grand Avenue from the limits of approximately 200’ feet south of Viki Lynn Place to Picadilly Drive.

 

Kimley-Horn, in conjunction with its geotechnical engineering subconsultant, Raba-Kistner, will be responsible to perform a Pavement Repair Report for Grand Avenue Parkway. The Project generally consists of completion of a visual pavement assessment, geotechnical investigation, existing utility assessment, and pavement engineering recommendations for Grand Avenue Parkway. This segment of Grand Avenue Parkway was reconstructed in 2017 and a previous Pavement Distress Evaluation of this segment was performed in April 2019 by Raba-Kistner. The pavement repair findings and recommendations (including repair locations) as prepared in the April 2019 report will be incorporated into the Final Pavement Repair Report for this project, which will be utilized to prepare PS&E for repair locations.

 

The specific Comprehensive Pavement Assessment and Repair Geotechnical Report will consist of the following items:

                     A summary of the field and laboratory sampling and testing

                     Boring logs and laboratory testing results

                     General site conditions to include geology, subsurface stratigraphy, groundwater conditions, and the presence of till material, if encountered

                     Engineering pavement section recommendations

                     Incorporate the findings from the 2019 Pavement Distress Study

                     Map of existing pavement conditions limits (rated 1-5)

                     Map of proposed limits of pavement rehabilitation recommendations

                     Photo inventory from the smartphone-based assessment (SBA) collection consisting of digital images captured approximately every ten (10) feet along the evaluated network

 

In addition to the geotechnical report, KHA will provide an opinion of probable construction cost estimate for the proposed recommended pavement sections and a presentation to City Council prior to commencing to design.

 

Staff recommends approval for the proposed initial phase professional services in order to have full and comprehensive assessment for the appropriate pavement repair recommendations prior to proceeding with PS&E in an effort for permanent repair of the current Grand Avenue Parkway section as previously constructed in 2017.  Staff will return to Council to report findings and request the necessary supplemental engineering services to complete the second phase for design PS&E, bidding and construction related to Grand Avenue Parkway.

 

Preparation of the final engineering construction documents (plans, specifications and estimate) shall include but not be limited to: project design, topographic surveys where required, geotechnical investigation report from phase 1, identification of utility conflicts, coordination with utility companies, engineer’s opinion of probable construction cost, project manual and any other items necessary to successfully reconstruct Grand Avenue for the sections as determined and may include additional segments that extend up to and not limited to E. Pflugerville Parkway.

A budget amendment will be forthcoming for initial funding of the project.

Prior City Council Action

During the prior October 13th City Council approved selection of Kimley-Horn and Associates as one of two consultants to provide professional engineering services.

 

The City of Pflugerville solicited requests for qualifications from engineering firms for the assessment of existing infrastructure, preliminary engineering, final design, permitting, bidding, construction administration, and construction materials testing for the 2020-2022 Pavement and Infrastructure Maintenance Projects.

Identified projects may include but are not limited to:

                       Grand Avenue Parkway

                       FY21-FY22 Pavement Maintenance Programs

 

City staff received ten (10) statements of qualifications (SOQs) on September 17, 2020 which were reviewed, ranked and scored. Halff Associates, Inc. and Kimley-Horn Associates, Inc. were selected as the most qualified firms for the projects.

 

Other prior City Council actions related to the limits of Grand Avenue Parkway as proposed include the following:

 

4/11/2017                     City Council approval for selection HVJ Associates as most qualified design engineering consultant

5/09/2017                     City Council approval to HVJ Associates for a Professional Services Agreement for engineering services related to Design PS&E, Bidding & Construction Administrative services in amount of $78,065.00

9/26/2017                     City Council award of Construction contract to Austin Materials as lowest responsive bidder in amount of $1,162,313.99

3/14 /2019                     City Council approval for a Professional Services Agreement for engineering services to Raba Kistner to perform non-destructive testing along Grand Avenue Parkway (within the same limits as proposed) in amount of $13,735.00

4/09/2019                     City Council approval for supplemental services for Raba Kistner to provide a Pavement Distress Evaluation in amount of $45,465.00

 

Deadline for City Council Action

Action is requested on October 27, 2020.

 

Funding Expected: Revenue __  Expenditure _X_  N/A __ 

Budgeted Item: Yes __ No _X*_  N/A __

*A budget amendment will be forthcoming for initial funding of the project.                      

Amount: _$69,994.20_______ 

1295 Form Required? Yes _X_ No __                     

Legal Review Required: N/A __ Required _X_ Date Completed: __10/16/2020__                                          

 

Supporting documents attached:

Professional Services Agreement

Project Location Map

Schedule

 

Recommended Action

Approve an agreement with Kimley-Horn and Associates in the amount of $69,994.20 for professional engineering services associated with the design, bidding, construction administration, and material testing for the Grand Avenue Parkway Pavement Repair Project and authorizing the City Manager to execute the same.