File #: 2021-0026    Version: 1 Name:
Type: Agenda Item Status: Approved
File created: 12/30/2020 In control: Engineering Dept
On agenda: 1/12/2021 Final action: 1/12/2021
Title: Approving Work Authorization No. 2020-6 with Seven Arrows Land Staff, LLC. in the amount of $78,750.00 for right-of-way services for the Sorento Wastewater Interceptor Phase 2 project.
Attachments: 1. Work Authorization_Sorento Int. Ph 2 Project, 2. ROW Exhibit_Sorento Int. Ph 2 Project, 3. Sorento Wastewater Interceptor Phase 2_Schedule, 4. Draft Presentation_2021-0026
Title
Approving Work Authorization No. 2020-6 with Seven Arrows Land Staff, LLC. in the amount of $78,750.00 for right-of-way services for the Sorento Wastewater Interceptor Phase 2 project.

Summary
On October 27, 2020, the City Council approved a professional engineering contract with CP&Y, Inc. for Design, Bidding and Construction Phase Services of the Sorento Wastewater Interceptor Phase 2 project, identified as Project 6 in the adopted 2020 Wastewater Master Plan.

The purpose of the Sorento Wastewater Interceptor Phase 2 project is to relieve the Weiss Lane Lift Station by diverting wastewater flow by gravity to the Carmel Lift Station, and ultimately to the future Wilbarger Creek Regional Wastewater Treatment Facility. This project will also include the decommissioning of the Verona Lift Station.

This design and construction phase services is comprised of Approximately 12,200 LF of 15” & 36” wastewater line along Upper Wilbarger Creek within new alignment that requires development of alternatives and final right-of-way acquisition. The proposed work authorization by & Arrows shall provide land services to support the City in execution of the Sorento Interceptor Phase 2 project. Services shall include:
* Obtaining Rights of Entry
* Title Research and Procurement
* Presenting Offers
* Negotiation and Closing of all types of land rights
- Right of Way
- Temporary Construction and Permanent Easement
- Property Acquisition
* Other services may also be included, as directed by City
- Assistance with Open Houses
- Similar Meetings with the public
- Presentations
- Other Real Estate and Property work as needed

The proposed services was previously identified within the CP&Y contract schedule (attached) and this action is requested to memo...