Discussion regarding an emergency generator power system for the Water Treatment Plant and Lake Pump Station.
Summary
This item has been included on the agenda to allow for discussion.
The Surface Water Treatment Plant currently has no backup power supply in the event of an extended power failure as was experienced from February 15, 2021 to February 17, 2021. This creates a significant risk for the City’s Public Water System as the plant produces most of the water that is used within the City. Due to this risk and the need to make the City's water system more resilient in the event of an emergency, the City Council approved a professional services agreement with Gupta and Associates, Inc. on September 22, 2020 to design the emergency generator power system. The design of the standby generator system has begun and the installation of the generators will allow the City to continue producing water in the event of a power failure affecting the Surface Water Treatment Plant and Lake Pump Station.
The project was included and listed as Water Treatment Plant Emergency Generator Power System in the 5-year Water Capital Improvements Program as shown in the FY 2020 budget.
Prior City Council Action
On September 22, 2020, City Council approved the selection of Gupta and Associates for professional services associated with the standby generator at the Water Treatment Plant and Lake Pump Station project and authorized the City Manager to execute a professional services agreement in the amount of $652,914 for design and engineering services for the emergency generator at the Water Treatment Plant and Lake Pump Station.
Deadline for City Council Action
No action to be taken.
Funding Expected: Revenue __ Expenditure __ N/A _X_
Budgeted Item: Yes __ No __ N/A _X_
Amount: _________
1295 Form Required? Yes __ No _X_
Legal Review Required: N/A _X_ Required __ Date Completed: _______
Recommended Action
This item is for discussion. No action will be taken.